City of Louisville, CO
Home MenuPermit Information
The Building Safety Division has adopted the Commercial 2021 IECC. See our adopted codes for more information.
Permit Submittal - Electronic
All permit submittals must be done electronically through our online portal.
Estimated Submittal Review Times | |
MEP - Single Trade: A/C, Furnace/Boiler, Water Heater MEP - Single Trade: Minor Electrical MEP - Single Trade: Minor Mechanical MEP - Single Trade: Minor Plumbing MEP - Single Trade: Sewer/Water Repair Minor Permit: Re-Roof Minor Permit: Re-Siding |
1-2 Business days |
MEP - Single Trade: Gas Line/Meter MEP - Single Trade: Hot Tub MEP - Single Trade: New Sewer/Water/Irrigation Tap Minor Permit: Accessory Structure (depends on scope of work) Minor Permit: Deck or Pergola Minor Permit: Demolition – Exterior or Whole Structure Minor Permit: Demolition – Interior Only Minor Permit: Fence Minor Permit: Foundation Repair Minor Permit: New Window/Door Minor Permit: Patio/Shaded Cover, Porch, or Carport Residential: Remodel Minor Permit: Retaining Wall Minor Permit: Signs / Temporary Signs |
1-2 Weeks for first review comments |
Minor Permit: Accessory Structure (depends on scope of work) Residential: Addition Residential: Footing/Foundation Residential: Mobile Home Residential: Multi Family Residential: Single Family Attached Residential: Single Family Detached |
4-6 Weeks for first review comments |
Commercial Permits | 4-6 Weeks for first review comments |
Roof Top Unit, Solar, Telecommunication | 2-3 Weeks for first review comments |
Construction Trailer |
1-5 Business days for first review comments 1-2 Weeks for first review comments |
Contractor License | 1-2 Business days |
Inspection Requests | Scheduled next business day |