Construction Updates

Print
Press Enter to show all options, press Tab go to next option

2017 City Construction Projects

Construction Update Map Legend 

This construction schedule is tentative and subject to change due to construction coordination, unknown site conditions, and weather.  The attached map indicates the improvement areas and tentative schedule.  attached map:

Downtown Construction

Construction projects continue in the downtown area and DELO Development.  

The South Street Underpass, is a new pedestrian connection between Old Town and East Louisville. The pedestrian underpass and a 70 space parking lot is now open to the public.  Project is 90% complete.

Remaining items of work includes right of way fencing and punch list work. 

The top layer of asphalt pavement will be installed on South/Front/Short Streets in early to mid 2018.

2017 Water Main Replacement Project

City Council Awarded the contract to Colorado Civil Infrastructure, Inc. Project is 95% complete.   Remaining items of work include punch list repairs, clean up and paperwork.  See construction project map (above) for locations.

Lee Ave./Walnut St. Utilities, Street Reconstruction and Spruce Street cul-de-sac Installations

Construction was awarded to H2 Development Services on June 6, 2017.  Utility, asphalt and concrete replacement on Lee Ave. and Walnut St. is complete. Remaining items of work include signage and clean up.    

2017 Storm System Maintenance Project

Colorado Civil was awarded the Contract.  Work should commence the week of December 11th on the pond near the railroad tracks.  See work locations above.

2017 Sanitary Sewer Lining Project

The project was awarded to Insituform Technologies, LLC.  Work began on November 16th.  Locations include N. Franklin Court and N. Franklin Avenue, west of Via Appia and then Sunset Drive and Longs Peak Drive south of S. Boulder Rd.  Work should be completed by the middle of December.

Sid Copeland Water Treatment Plant (SCWTP) High Zone/Mid Zone Pump Station

Project was awarded to Integrated Water Services.  construction includes the installation of a new water main through the North Open Space from SCWTP to Centennial Drive.  Work is scheduled from December 2017 to February 2018. Multiple single day trail closures and temporary trail segments will be encountered.

 We would like to thank everyone for your patience and understanding during construction and remind everyone to exercise caution when driving, biking, or walking through a construction zone.